Rate of implementation commitments

81.5% rate of implementation commitments to date
8.8% rate of implementation commitments from December 2019 to December 2022 without capacity building support
9.7% rate of implementation commitments by December 2022 upon receipt of capacity building support

Ratified on the 22 February 2017

Notification of indicative and definitive dates for implementation

Category B Category C
Notified indicative dates Yes Yes
Notified definitive dates Yes Yes

Notification of technical assistance required

Category C
Notified technical assistance required Yes

Category C analysis

Jordan has requested assistance and support for capacity building for a total number of 7 measures. View Information

Notifications and other documents

Symbol Date Received Description
G/TFA/N/JOR/1 2018-06-07 Categories B and C notification   EN   FR   ES